Softwood will be chipped and dried on site before being fed via conveyors into a series of 10 gasifiers. A superheating process creates the required gas to power turbines that feed energy back into the grid.

Acharn biomass facility panoramic

Preparing a hillside site

The first phase of the project was to construct an access road, junction upgrade and carry out clear felling of the timber growing on the hillside.

Initial earthworks involved a substantial cut and fill operation so that a platform on which to construct the facility could be built.

Due to the properties of the existing soils we had to carry out extensive lime stabilisation to improve the bearing capacity of the formation. In addition, all rock excavated from the site was processed and reused in the construction of the platform and on-site roads.

We constructed a series of 6m deep reinforced concrete bunkers to house hoppers for the dried, chipped softwood that is then fed into the gasifiers via conveyors.

As part of this project we are building a 1200m2, 13m high steel framed structure that will house the gasifier units and associated process plant along with a substation and all associated plant and equipment to support the facility.

 

Related news

  • From wasteland to community garden

    From wasteland to community garden

    The Spanish City Dome team has transformed a patch of waste ground into an attractive and useful community garden.
  • Robertson Specialist Division wins SSE c...

    Robertson Specialist Division wins SSE c...

    Robertson Specialist Division has secured work for SSE worth around £560,000 – the first time it will serve as a main contractor.
  • Robertson joins Buy Social Corporate Cha...

    Robertson joins Buy Social Corporate Cha...

    Today, Robertson has joined the Buy Social Challenge, in addition to our membership of Social Enterprise UK.

Related blog posts

  • Back to the floor: engineering apprenticeships

    Back to the floor: engineering apprenticeships

    Robertson Engineering Services Managing Director, Darren Clarke, meets with mechanical and electrical engineering apprentices.
  • A route in to modern apprenticeships

    A route in to modern apprenticeships

    Robertson’s Dundee office has seen various young people start apprenticeships and progress in their careers in the past few years.
  • The path forward from apprenticeships

    The path forward from apprenticeships

    Mike Turner originally started as a joiner on a 1-year YTS programme and is now Managing Director of Robertson Timber Engineering.