Lister Learning and Teaching Centre
Get in touch
Summary
Phased work on a tight city centre site
Robertson completed two main phases of work to create two teaching and lecture facilities for medical students at the University of Edinburgh at Roxburgh Place, along with better access and circulation space between the two buildings.
The project was procured through the Scape Major Works framework (now superseded by Major Works Scotland), part of the National Construction framework. It was delivered by Robertson in partnership with Willmott Dixon.
Using this framework enabled a swift turnaround from the preconstruction stage to work commencing on site, meaning the project could be delivered in the short timeframe required.
Tight site and timeframe
The University had an urgent need for additional teaching spaces due to an increased number of students in the medical faculty. In addition, the site was situated on a cobbled street in Edinburgh's busy, historic city centre, making logistics challenging.
There was limited space for site cabins, material deliveries and lay-down areas. The tight site and short timeframe meant that careful attention had to be paid to the construction programme, while also scheduling deliveries to minimise disruption to local residents and businesses.
O'Hara added: "The challenging construction programme was managed to deliver Phase 1 of the project on schedule, meaning the University took possession of much-needed additional teaching space for over 670 students in time for the new academic year. Throughout this process Robertson have maintained a high level of professionalism and have continued to execute the UoE's vision for this unique project."
Phased handover to release teaching spaces
The project involves a series of alterations and refurbishments to existing buildings, as well as construction of a new five-storey link building between the two existing buildings. Phase 1 was handed over on time in September 2017, on schedule for the academic year. This comprises 18 teaching rooms and three seminar rooms, with associated break-out space. These new facilities accommodate 670 students.
Work included:
- New temporary entrance into Lister building from Roxburgh Place.
- Designing and completing temporary works within lecture theatre.
- Additional partitions screening Phase 1 works from later Phases 2 and 4.
- Reconfiguration of M&E services.
- Procuring and creating new temporary reception area including raised floors, platforms, partitions, external and internal doors, and finishes.
The final Phase of the project was handed over on time in September 2018, also on schedule for the academic year. This phase finalised the refurbishment of the Pfizer building and completed the new link structure. We removed, the Phase 1 temporary works along with temporary partitions & screens, reconfigured M&E services, and transformed the temporary entrance into a modern lecture theatre.
Enhancing learning during construction
During the project, construction students from Edinburgh College took their learning out of the classroom and onto site, as part of an initiative that covered several projects across the city, including the Lister Learning and Teaching Centre.
Second-year HND Construction Management student Lewis McCann (21) spent a week with the team at Roxburgh Place, being shown the ropes of managing a live site.
"The whole experience has helped put my studies into perspective. I really enjoyed the initial induction and walk-around the site as it gave me a feel for the wider project and being given the chance to participate in meetings added an additional element to my learning, as it was the first opportunity I've had to do so."
The full programme of education and training included:
- 69 student visits to site
- 60 college student workshops
- 14 university students visiting site
- 21 work experience placements for people under 17 years old
- 33 work experience placements for people over 18 years old
- 15 apprentices, totalling 104 weeks of experience
- 13 NVQs completed
Safety, health and environment, KPI's
- Zero RIDDORs, accidents or incidents
- 98% of waste from site recycled (target 95%)
- Considerate Constructors Score: 42/50
- 56% local spend within 10 miles of the site
- 67% local spend within 20 miles of the site
- 81% local spend within 40 miles of the site
Education and training
- School/college/university site visits: 81 students
- School/college workshops: 60 students
- University research projects: 9 students
- Work experience 15-17 years:- 22.4 weeks
- Work experiences 18+ years: 43.2 weeks
- Apprentices: 104
- National Vocational Qualifications: 13