Newcastle hospitals refurbishment

Details
X

Get in touch

Summary

Sector
Healthcare
Value
£4.3m
Location
Newcastle-upon-Tyne
Status
Completed
Customer
The Newcastle-upon-Tyne Hospitals NHS Foundation Trust
Completion
April 2019
Get social and share

For a better patient and staff experience

We’re proud to shape healthcare environments that improve the patient experience and support staff to deliver the very best they can.

Our projects in Newcastle highlight the extent of our capabilities and work in live hospital environments where the health and safety of staff, patients and visitors is our top priority.

  • Dental Hospital Oral Surgery Department (£1.4m, 6 months): Refurbishment of department including removal of external ACM cladding and installation of specialist M&E including vac and air systems, medical gases and dental chairs.
  • Cav Boiler Plant Works (£480k, 5 months): Replaced two plant rooms including installation of 300m of new main gas pipes, with trench works carried out on live roads.
  • Cherry Burn Ward (£570k, 7 months): Converted former stroke rehabilitation ward into a 1,200 m2 suite of outpatient clinical accommodation, offices, with a new GAIT Laboratory.

Freeman Hospital

  • DSC Plant (£370k, 3 months): Replaced boilers, installing temporary boilers during works to ensure provision.
  • Lift Lobby (£280k, 2 months): Design and refurbishment of level 3 lobby, working through the night to minimise disruption.
  • Junior Doctors Accommodation (£480k, 1 month): Design and conversion of disused hydro pool area into mess area for Junior Doctors.
  • Executive Suite (£270k, 2 months): Refurbishment of high traffic employee area.
  • Data Centre (£480k, 1 month): Design and upgrade of data centre resilience package including power, trenching and cooling.